EĞLENCE II HPP / 27.2 MWe Egenda Ege Energy Production Co.

Company Information

Legal Entity

Egenda Ege Power Production Co.

Founded

14.03.1997

Investment Cost

72.472.380 TL/40.930.973 $

Capital

210.000.000 TL

Annual Production Capacity

78 GWh/Year

Installed Capacity

28 MWm / 27,2 MWe

Facility Type

Hydroelectric (River Type)

License Acquired

27.12.2007

Location (Province/District)

Adana / Karaisalı

Commercial Operation

April 2013

Operational Model/Duration

Production / 49 Year

Unit Type/Manufacturer

Francis (Vertical)/Flovel

Number of Units

3 (5,23 + 2 x 10,98 MWe)

Net Head and Flow Rate

169 m – 17,4 m3/sec

Connection Type

Substation 154 kV – 19.8 km